Key dates of the NH1 project
-
2019
2019
- Creation of Normandie Hydroliennes (NH) and transfer of authorisations and project concessions
- Launch of the TIGER Project
-
2020- 2022
2020-2022
- Evaluation of the site
- Environmental studies
- Project development and engineering design of technology
-
2023
2023
- Completion of the TIGER Project
- Consent variation application
- Public stakeholder engagement activities
-
2025
from 2025
- Start of 4 year environmental monitoring programme
-
2025-2026
2025-2026
- Construction and installation of onshore equipment
- Launch of turbine fabrication and assembly in Cherbourg
-
2026
2027
- Installation of turbines and subsea hub
- Laying of cable and grid connection
- Commissioning of system
- Start of electricity production