Key dates of the NH1 project

  • 2019

    2019

    • Creation of Normandie Hydroliennes (NH) and transfer of authorisations and project concessions
    • Launch of the TIGER Project
  • 2020- 2022

    2020-2022

    • Evaluation of the site
    • Environmental studies
    • Project development and engineering design of technology
  • 2023

    2023

    • Completion of the TIGER Project
    • Consent variation application
    • Public stakeholder engagement activities
  • 2025

    from 2025

    • Start of 4 year environmental monitoring programme
  • 2025-2026

    2025-2026

    • Construction and installation of onshore equipment
    • Launch of turbine fabrication and assembly in Cherbourg
  • 2026

    2027

    • Installation of turbines and subsea hub
    • Laying of cable and grid connection
    • Commissioning of system
    • Start of electricity production